Chilean Naval Construction
1925 Fourth Quarter Report
October 1 - December 31
A. Factories
3/7 factories = 3,000t of material + 0t stockpiled + = 3,000t available
3000t are used, and 0t transferred, leaving a stockpile of 0t.
2/7 factories (committed) = 0.2 infrastructure pts + 0.2 pts for full year +
2/7 factories (flexible) = 0.2 pts = 0.6 pts available
B. Infrastructure Development
Continued construction of Type 3 slip at Talcahuano
0.4 points alotted = 3 total/3 needed = 0 needed to complete.
Continued construction of Type 2 drydock at Talcahuano
0.2 points alotted = 2.3 total/3 needed = 0.7 needed to complete
C. Naval Development and Construction
at Talcahuano:
S3: Completed and construction crews being trained.
S2: Continued contruction on PC-5/CL-5 Maunga Terevaka (1,500 tons delivered) 6735 tons originally needed, will require 472 day to complete (finishes during Q2/1926) - 2,187 tons remaining to complete.
S1: idle
D2: *under construction
D2: idle
D0: idle
at Valparaiso:
S1: Continued contruction on CL-4 Guardia Marina Hyatt (1,000 tons delivered) 4,191 tons originally needed, will require 396 days to complete (finishes during Q1/1926) - 143 tons needed to complete.
S0: idle
D1: Laided down new Collier Araucano (500 tons delivered) 5,677 tons originally needed, will require 441 days to complete (finishes during Q1/1927) - 5,177 tons needed to complete.
at Mejillones:
S0: idle
S0: idle
D0: idle
Commericial shipyards:
idle
D. Transactions
Purchase of 203 mm cannon from Italy appoved. Payment to be made upon delivery of the first units in Q2/1926.
E. Other Notes
DD-18 Capitan Simpson completed and working up.
DL-1 Teniente Riquelme completed and working up.
DL-2 Teniente Videla completed and working up.
Collier Araucano laid down at Valparaiso
Experiance in the Western Pacific has shown the Chilean Navy that they need a few additional colliers and oilers. Maipo and Rancangua will be replaced as support ships as the new Araucano-class comes off the slips. As such the Destroyer projects have been placed on hold until the cruiser Guardia Marina Hyatt is finished.
F. Updated Order of Battle, December 31, 1925
Note:
Y)+Z = completed (under repair/refit) + under construction
Dreadnought Battleships------2(0)+0
Predreadnoughts----------------2(0)+0
Coast Defense Ships-----------1(0)+0
Armoured Cruisers--------------2(0)+0
Light Cruisers--------------------3(0)+1
Protected Cruisers--------------3(0)+1
Destroyers------------------------8(0)+0 {1,200 tons std and up}
Destroyers (old)-----------------7(0)+0 {under 1,200 tons std: old}
Light Destroyers-----------------2(0)+0 {under 1,200 tons std: new}
Submarines-----------------------6(0)+0
Colliers-----------------------------1(0)+1
Sail Training Sloop---------------1(0)+0
Transports-------------------------2(0)+0
-Emergency Use-
Patrol Boats---------11(0)+0
Transports-----------12(0)+0
Museum Ships--------1(0)+0