Chilean Naval Construction
1933 Second Quarter Report
April 1 - June 30, 1933
A. Factories
5/7 factories = 5,000t of material + 2,500 for 50% wartime production.
6,500t are used, and 1,000t transferred, leaving a stockpile of 0t.
2/7 factories (committed) = 0.3 infrastructure pts
0/7 factories (flexible) = 0.0 pts = 0.3 pts available
B. Infrastructure Development
Factory #8 continues construction: 7.3 of 10
C. Naval Development and Construction
at Talcahuano:
S3: Construction continues on Armored Cruiser "General O'Higgins" (3,000 tons delivered) 22,745 tons needed, will require 790 days to complete (finishes during Q1/1935) - 16,745 tons needed to complete
S2: Construction continues on "Light" Cruiser Antofagasta (3,000 tons delivered) 9,747 tons needed, will require 514 days to complete. (finishes Q1/1934) - 5,648 tons needed to complete
S1: Construction continues on heavy destroyer Almirante Zero (0 tons delivered) 1,986 tons needed, will require 320 days to complete. (finishes Q2/1933) - 0 tons needed to complete. Finished
D3: idle
D2: idle
D2: Construction continues on heavy destroyer "Almirante Lynch" (500 tons delivered) 1,986 tons needed, will require 320 days to complete. (finishes Q4/1933) - 512 tons needed to complete.
D0: idle
at Valparaiso:
S1: Construction continues on destroyer Capitan Thompson (0 tons delivered) 1,389 tons needed, will require 305 days to complete. (finishes Q2/1933) - 0 tons needed to complete. Finished
S1: Construction continues on destroyer Capitan Lira (0 tons delivered) 1,389 tons needed, will require 305 days to complete. (finishes Q2/1933) - 0 tons needed to complete. Finished
D1: Construction continues on destroyer Capitan Toro (0 tons delivered) 1,389 tons needed, will require 305 days to complete. (finishes Q2/1933) - 0 tons needed to complete. Finished
at Mejillones:
S0: idle
S0: idle
D0: idle
Commericial shipyards:
idle
D. Transactions
Chile has put forth interest in the purchase of the Nordmark Battlecruiser Folkunga Lion in 1933 for a cost of 4,000 tons of material. 1,000 tons sent to Nordmark Q2/1933. (2,000 tons remaining)
E. Other Notes
Construction continues on Heavy Armored Cruiser "General O'Higgins" (AC-5).
Construction continues on Heavy Destroyer "Almirante Lynch" (DD-20).
Construction continues on "Light" Cruiser Antofagasta (CL-9).
Heavy Destroyer Almirante Zero (DD-19) construction completed. On trails.
(DD-20 and DD-21 are reserved for the Almirante Lynch and Almirante Condell as replacements for the current vessels with those names.)
Destroyer Capitan Thompson (DD-22) construction completed. On trails.
Destroyer Capitan Lira (DD-23) construction completed. On trails.
Destroyer Capitan Toro (DD-24) construction completed. On trails
Heavy Armored Cruiser Capitan Oyama (AC-4) construction completed. On trails.
Dreadnought Almirante Cochrane's rebuild completed. On trials until May.
Work continues on the "15 inch/51 caliber" cannon project, which has expanded into the Oyama-Pacifica Ordinance Work factory.
Chile is on a full war footing in Q2/1933 as stated in Q1/1932 report.
F. Updated Order of Battle, June 30, 1933
Note: W(X)+Y(Z) = completed (under repair/refit) + under construction (...by a foreign power)
Dreadnought Battleships------2(0)+0
Dreadnought Battlecruisers---0(0)+0(1)
Predreadnoughts----------------2(0)+0
Coast Defense Ships-----------1(0)+0
Aircraft Carrier-------------------1(0)+0
Armoured Cruisers--------------3(0)+1
Heavy Cruiser--------------------2(0)+0
Light Cruisers--------------------6(0)+1
Protected Cruisers--------------2(0)+0
Floatplane Cruisers-------------1(0)+0
Destroyers------------------------12(0)+1 {1,200 tons std and up}
Light Destroyers-----------------6(0)+0 {under 1,200 tons std}
Submarines-----------------------8(0)+0
Floatplane Carriers--------------2(0)+0
Subchasers------------------------24(0)+0
Tenders-----------------------------2(0)+0
Colliers-----------------------------2(0)+0
Sail Training Sloop---------------1(0)+0
Transports-------------------------2(0)+0
-Emergency Use-
Patrol Boats---------11(0)+0
Transports-----------12(0)+0
Museum Ships--------1(0)+0
This post has been edited 1 times, last edit by "Ithekro" (Jan 15th 2007, 12:13am)