Quoted
Originally posted by Brockpaine
Size Type Length (m) Length (ft) Cost Turnaround time
0 Slip 70m 230ft 0.5IP 1 week
0 Dry-dock 70m 230ft 1IP 1 week
.5 Slip 95m 312ft .75IP 1 week
.5 Dry-dock 95mft 312 1.5IP 2 weeks
1 Slip 120m 393ft 1IP 2 weeks
1 Dry-dock 120m 393ft 2IP 2 weeks
1.5 Slip 145m 476ft 1.5IP 2 weeks
1.5 Dry-dock 145m 476ft 2.5IP 3 weeks
2 Slip 170m 557ft 2IP 3 weeks
2 Dry-dock 170m 557ft 3IP 3 weeks
2.5 Slip 195m 640ft 2.5IP 3 weeks
2.5 Dry-dock 195m 640ft 3.5IP 4 weeks
3 Slip 220m 721ft 3IP 4 weeks
3 Dry-dock 220m 721ft 4IP 4 weeks
3.5 Slip 245m 804ft 3.5IP 4 weeks
3.5 Dry-dock 245m 804ft 4.5IP 5 weeks
4 Slip 270m 885ft 4IP 5 weeks
4 Dry-dock 270m 885ft 5IP 5 weeks
4.5 Slip 295m 968ft 4.5IP 5 weeks
4.5 Dry-dock 295m 968ft 5.5IP 6 weeks
5 Slip 320m 1049ft 5 6 weeks
5 Dry-dock 320m 1049ft 6 6 weeks
This post has been edited 1 times, last edit by "Brockpaine" (Dec 16th 2008, 8:08am)
Forum Software: Burning Board® Lite 2.1.2 pl 1, developed by WoltLab® GmbH