Dear visitor, welcome to WesWorld. If this is your first visit here, please read the Help. It explains in detail how this page works. To use all features of this page, you should consider registering. Please use the registration form, to register here or read more information about the registration process. If you are already registered, please login here.

1

Thursday, March 2nd 2006, 10:18am

Greece - 1930 Q1

[SIZE=3]Greek Report[/SIZE][SIZE=3] - 1930 - Q1[/SIZE]


Total Factories: ->15 Factories
Fixed IP ->1 Factories
Flexible IP ->0 Factories
Ship Tonnage ->14 Factories
Bonus IP (Q4) ->0 IP


Infrastructure Projects
New T1 Dock at Souda Bay ->0.1 points this Q 1.6 points total 80% Complete[/B]

IP Not allocated ->0points this Q


Ships being Scrapped ->none

Ships Scrapped (prior 2Q) ->none

Production -> £3,733,333
From Scrap ->£0
Transferred from last Q ->£0
Used -> £3,646,957
Transfer to next Q -> £86,376


Program Alpha - Large Ship Construction


AC-4 Thaumas - Seaplane Carrier
Builder: Yard - Attica Slip/Dock- T3 Dry
Full Load Displ: 17006 tons Laid Down: 01/Mar/29
Launched: 07/Jan/30 Clear Slip: 04/Feb/30 Completed: 20/Apr/31 Entered Service: 17/Oct/31
£227,945 this Q £1,120,945 total 59% Complete

B-2 Salamis rebuild - Battleship
Builder: Yard - Suda Bay Dock- T4 Dry
Full Load Displ: 16295 tons Laid Down: 01/Jan/30
Launched: 31/Oct/30 Clear Slip: 28/Nov/30 Completed: 29/Jan/32 Entered Service: 27/Jul/32
£656,184 this Q £656,184 total 12% Complete

C-30 Psara - Cruiser
Builder: Yard - Attica Slip/Dock- T3 Dry
Full Load Displ: 10187 tons Laid Down: 01/Jan/30
Launched: 19/Aug/30 Clear Slip: 16/Sep/30 Completed: 30/Jul/31 Entered Service: 26/Jan/32
£464,343 this Q £464,343 total 16% Complete


Program Gamma - Medium Ship Construction
AS-3 Hekate - Submarine Transport
Builder: Yard - Suda Bay Slip/Dock- T2 Dry
Full Load Displ: 4500 tons Laid Down: 15/Mar/29
Launched: 24/Aug/29 Clear Slip: 21/Sep/29 Completed: 24/Apr/30 Entered Service: 21/Oct/30
£240,000 this Q £960,000 total 96% Complete

C-26 Iraklion - Escort Cruiser
Builder: Yard - Attica Slip/Dock- T2 Slip
Full Load Displ: 5769 tons Laid Down: 31/Mar/29
Launched: 24/Sep/29 Clear Slip: 22/Oct/29 Completed: 17/Jun/30 Entered Service: 14/Dec/30
£302,418 this Q £593,898 total 43% Complete

D-37 Massavetas - Destroyer
Builder: Yard - Attica Slip/Dock- T2 Dry
Full Load Displ: 1482 tons Laid Down: 01/Jul/29
Launched: 03/Nov/29 Clear Slip: 01/Dec/29 Completed: 11/May/30 Entered Service: 07/Nov/30
£154,081 this Q £446,281 total 92% Complete

D-38 Kolokotronis - Destroyer
Builder: Yard - Attica Slip/Dock- T1 Dry
Full Load Displ: 1515 tons Laid Down: 01/Jan/30
Launched: 07/May/30 Clear Slip: 04/Jun/30 Completed: 12/Nov/30 Entered Service: 11/May/31
£236,469 this Q £236,469 total 32% Complete

D-39 Botsaris - Destroyer
Builder: Yard - Attica Slip/Dock- T1 Slip
Full Load Displ: 1515 tons Laid Down: 01/Jan/30
Launched: 07/May/30 Clear Slip: 04/Jun/30 Completed: 12/Nov/30 Entered Service: 11/May/31
£236,469 this Q £236,469 total 32% Complete


Program Epsilom - Escort Ship Construction
G-15 Arete - Gunboat
Builder: Yard - Attica Slip/Dock- T1 Slip
Full Load Displ: 3078 tons Laid Down: 31/Mar/29
Launched: 22/Aug/29 Clear Slip: 19/Sep/29 Completed: 28/Mar/30 Entered Service: 24/Sep/30
£162,213 this Q £497,653 total 83% Complete

G-16 Diomedes - Gunboat
Builder: Yard - Attica Slip/Dock- T1 Slip
Full Load Displ: 3078 tons Laid Down: 31/Mar/29
Launched: 22/Aug/29 Clear Slip: 19/Sep/29 Completed: 28/Mar/30 Entered Service: 24/Sep/30
£162,213 this Q £497,653 total 83% Complete

F-24 Atreus - Frigate
Builder: Yard - Patra Slip/Dock- T1 Dry
Full Load Displ: 3053 tons Laid Down: 31/Mar/29
Launched: 22/Aug/29 Clear Slip: 19/Sep/29 Completed: 27/Mar/30 Entered Service: 23/Sep/30
£150,909 this Q £486,349 total 87% Complete

F-22 Calydon - Frigate
Builder: Yard - Patra Slip/Dock- T1 Slip
Full Load Displ: 3053 tons Laid Down: 31/Mar/29
Launched: 22/Aug/29 Clear Slip: 19/Sep/29 Completed: 27/Mar/30 Entered Service: 23/Sep/30
£150,909 this Q £486,349 total 87% Complete

F-23 Melampus - Frigate
Builder: Yard - Salamis Slip/Dock- T1 Dry
Full Load Displ: 3053 tons Laid Down: 31/Mar/29
Launched: 22/Aug/29 Clear Slip: 19/Sep/29 Completed: 27/Mar/30 Entered Service: 23/Sep/30
£150,909 this Q £486,349 total 87% Complete

M-5 Chios - Minelayer
Builder: Yard - Volos Slip/Dock- T1 Dry
Full Load Displ: 3062 tons Laid Down: 31/Mar/29
Launched: 22/Aug/29 Clear Slip: 19/Sep/29 Completed: 27/Mar/30 Entered Service: 23/Sep/30
£139,125 this Q £474,565 total 93% Complete


Minor Ship Construction
MS-12 Pegaiai - Minesweeper
Builder: Yard - Attica Slip/Dock- T0 Slip
Full Load Displ: 1034 tons Laid Down: 31/Mar/29
Launched: 29/Jul/29 Clear Slip: 26/Aug/29 Completed: 26/Jan/30 Entered Service: 25/Jul/30
£75,382 this Q £216,122 total 95% Complete

T-26 Poluphemos - Torpedo Boat
Builder: Yard - Thessalonica Slip/Dock- T0 Slip
Full Load Displ: 600 tons Laid Down: 31/Mar/29
Launched: 24/Jul/29 Clear Slip: 21/Aug/29 Completed: 13/Jan/30 Entered Service: 12/Jul/30
£43,200 this Q £270,000 total 100% Complete

T-27 Pegasos - Torpedo Boat
Builder: Yard - Thessalonica Slip/Dock- T0 Slip
Full Load Displ: 600 tons Laid Down: 31/Mar/29
Launched: 24/Jul/29 Clear Slip: 21/Aug/29 Completed: 13/Jan/30 Entered Service: 12/Jul/30
£94,186 this Q £207,586 total 77% Complete