German Naval Construction Programme, Second Quarter 1941
A. Factories
Factories: 31
Available: 31
Producing Warship Material: 31
Tonnage Produced: 31,000
Producing Infrastructure (Committed): 0
Producing Infrastructure (Non - Committed): 0
Infrastructure Points Produced: 0.0
Bonus IP for Committed Factories: 0.0
Total IP Available: 0.0
Tonnage Produced: 31,000
Tonnage Transferred In: 0
Tonnage Received in Payment: 11,570
Tonnage Reclaimed From Scrap: 0
Tonnage Previously Stockpiled: 4,730
Total Tonnage Available: 47,300
Tonnage Transferred Out: 0
Tonnage Paid: 0
Tonnage Used in Construction: 43,870
Tonnage Remaining for Stockpile: 3,430
B. Infrastructure Development
None this quarter
C. Naval Development and Construction
Bremerhaven
Dock Nr.1 - Type 3.0 – Idle
Slip Nr.1 - Type 3.0 – Idle
Slip Nr.2 - Type 1.0 – Destroyer Marburg: Laid down 1 Jan 1941: Requires 1,916 tons, 0 tons previously consumed; receives 480 tons, 1,436 tons remaining
Slip Nr.3 - Type 1.0 - Destroyer Konstanz: Laid down 1 Jan 1941: Requires 1,916 tons, 0 tons previously consumed; receives 480 tons, 1,436 tons remaining
Pierside:
Light cruiser Rostock: Requires 9,790 tons, 7,805 tons previously consumed; receives 1,561 tons; 424 tons remaining
Light cruiser Stralsund: Requires 9,790 tons, 7,805 tons previously consumed; receives 1,561 tons; 424 tons remaining.
Cuxhaven
Dock Nr.1 - Type 4.0 – Aircraft carrier Scharnhorst: Laid down 1 Jan 1941 – Requires 26,835 tons, 2,250 tons previously consumed; receives 2,250 tons; 22,335 tons remaining
Dock Nr.2 - Type 2.0 - Idle
Slip Nr.1 – Type 4.0 – Idle
Slip Nr.2 – Type 2.0 – Idle
Slip Nr.3 – Type 1.0 – Destroyer Tubingen: Laid down 1 Jan 1941: Requires 1,916 tons, 0 tons previously consumed; receives 480 tons, 1,436 tons remaining
Slip Nr.4 – Type 1.0 – Destroyer Weilheim: Laid down 1 Jan 1941: Requires 1,916 tons, 0 tons previously consumed; receives 480 tons, 1,436 tons remaining
Pierside:
Battleship Ostmark: Requires 63,165 tons; 57,772 tons previously consumed; receives 0 tons; 5,393 tons remaining
Battleship Preuzen: Requires 63,165 tons; 51,207 tons previously consumed; receives 1,313 tons; 10,645 tons remaining
Brazilian Battlecruiser Sao Paulo: Requires 35,785 tons; 31,018 tons previously consumed; receives 2,386 tons; 2,381 tons remaining
Brazilian Battlecruiser Rio de Janiero: Requires 35,785 tons, 26,246 tons previously consumed; receives 2,386 tons, 7,153 tons remaining
Destroyer Koblenz: Launched 31 Jan 1941 – Requires 1,916 tons, 960 tons previously consumed; receives 480 tons, 476 tons remaining
Destroyer Wetzlar: Launched 31 Jan 1941 – Requires 1,916 tons, 960 tons previously consumed; receives 480 tons, 476 tons remaining
Fleet replenishment ship Donau: Launched 11 Feb 1941 – Requires 7,935 tons, 3,960 tons previously consumed; receives 1,325 tons; 2,635 tons remaining
Fleet replenishment ship Werra: Launched 11 Feb 1941 – Requires 7,935 tons, 3,960 tons previously consumed; receives 1,325 tons; 2,635 tons remaining
Hamburg
Slip Nr.1 – Type 2.0 – Fleet replenishment ship Neckar: Laid down 15 Jan 1941; Requires 7,935 tons, 1,325 tons previously consumed; receives 1,325 tons; 5,285 tons remaining
Slip Nr.2 – Type 2.0 – Fleet replenishment ship Ruhr: Laid down 15 Jan 1941; Requires 7,935 tons, 1,325 tons previously consumed; receives 1,325 tons; 5,285 tons remaining
Slip Nr.3 – Type 1.0 – Minesweeper Schwielowsee: Laid down 1 Apr 1941; Requires 459 tons, 0 tons previously consumed; receives 250 tons, 209 tons remaining; Launched 31 May 1941
Slip Nr.4 – Type 1.0 – Minesweeper Werbellinsee: Laid down 1 Apr 1941; Requires 459 tons, 0 tons previously consumed; receives 250 tons, 209 tons remaining; Launched 31 May 1941
Pierside
Destroyer Paderborn: Launched 11 Oct 1940; Requires 1,916 tons, 1,440 tons previously consumed; receives 476 tons, 0 tons remaining; Completed 30 Apr 1941 and commences trials
Destroyer Gottingen: Launched 11 Oct 1940; Requires 1,916 tons, 1,440 tons previously consumed; receives 476 tons, 0 tons remaining; Completed 30 Apr 1941 and commences trials
Minesweeper Fleesensee; Launched 2 Mar 1941; Requires 459 tons, 250 tons previously consumed; receives 209 tons, 0 tons remaining; completed 19 May 1941 and commences trials
Minesweeper Rhinsee; Launched 2 Mar 1941; Requires 459 tons, 250 tons previously consumed; receives 209 tons, 0 tons remaining; completed 19 May 1941 and commences trials
Kiel
Dock Nr.1 – Type 4.0 – Aircraft carrier Gneisenau: Laid down 1 Jan 1941 – Requires 26,835 tons, 2,250 tons previously consumed; receives 2,250 tons; 22,335 tons remaining
Dock Nr.2 – Type 2.5 – Idle
Dock Nr.3 – Type 2.0 – Idle
Dock Nr.4 – Type 0.0 – Idle
Slip Nr.1 – Type 4.0 – Idle
Slip Nr.2 - Type 3.0 – Idle
Slip Nr.3 – Type 1.0 – Idle
Slip Nr.4 – Type 1.0 – Destroyer Lindau: Laid down 1 Jan 1941: Requires 1,916 tons, 480 tons previously consumed; receives 480 tons, 960 tons remaining; Launched 3 May 1941
Slip Nr.5 – Type 1.0 – Destroyer Schleswig: Laid down 1 Jan 1941: Requires 1,916 tons, 480 tons previously consumed; receives 480 tons, 960 tons remaining; Launched 3 May 1941
Pierside
Battleship Sachsen: Requires 63,165 tons; 55,146 tons previously consumed; receives 0 tons; 5,393 tons remaining
Battleship Bayern: Requires 63,165 tons; 51,207 tons previously consumed; receives 1,313 tons; 10,645 tons remaining
Argentine Battlecruiser Viencente de Mayo: Requires 35,790 tons, 33,404 tons previously consumed; receives 2,386 tons, 0 tons remaining; Completed 5 Jun 1941 and commences trials
Argentine Battlecruiser Constelacion: Requires 35,790 tons, 26,246 tons previously consumed; receives 2,386 tons, 7,158 tons remaining
Light Cruiser Magdeburg: Requires 9,790 tons, 9,366 tons previously consumed; receives 424 tons, 0 tons remaining; Completed 17 Apr 1941 and commences trials
Light Cruiser Novara: Launched 28 Mar 1941: Requires 7,576 tons, 3,795 tons previously consumed; receives 1,265 tons, 2,516 tons remaining
Light Cruiser Custozza: Launched 28 Mar 1941: Requires 7,576 tons, 3,795 tons previously consumed; receives 1,265 tons, 2,516 tons remaining
Wilhelmshaven
Dock Nr.1 - Type 3.0 – Idle
Dock Nr.2 – Type 0.0 – Idle
Slip Nr.1 – Type 1.0 – Fleet Submarine U-121: Laid down 1 Jan 1941; Requires 1,385 tons, 350 tons previously consumed; receives 350 tons, 685 tons remaining
Slip Nr.2 – Type 0.5 – Coastal Submarine U-201: Laid down 1 Jan 1941; Requires 506 tons, 150 tons previously consumed; receives 150 tons, 206 tons remaining; Launched 21 Jun 1941
Slip Nr.3 – Type 0.5 – Coastal Submarine U-202: Laid down 1 Jan 1941; Requires 506 tons, 150 tons previously consumed; receives 150 tons, 206 tons remaining; Launched 21 Jun 1941
Pierside:
Light Cruiser Lubeck: Requires 9,790 tons, 9,366 tons previously consumed; receives 424 tons, 0 tons remaining; Completed 17 Apr 1941 and commences trials
Peruvian Light Cruiser Ancash: Launched 28 Mar 1941; Requires 9,757 tons, 4,800 tons previously consumed; receives 1,600 tons, 3,357 tons remaining
Vienna:
Dock Nr.1 – Type 0.0 – Idle
Slip Nr.1 – Type 0.0 – Idle
Memel:
Dock Nr.1 – Type 1.0 – Idle
Slip Nr.1 – Type 1.0 – Icebreaker Castor: Laid down 1 Jan 1941; Requires 2,184 tons, 546 tons previously consumed; receives 546 tons, 1,092 tons remaining; Launched 31 May 1941
Slip Nr.1 – Type 1.0 – Icebreaker Pollux: Laid down 21 Jun 1941; Requires 2,184 tons, 0 tons previously consumed; receives 546 tons, 1,638 tons remaining
Slip Nr.2 – Type 0.0 – Netlayer Norderney: Laid down 1 Apr 1941; Requires 455 tons, 0 tons previously consumed; receives 255 tons, 200 tons remaining; Launched 26 May 1941
Slip Nr.3 – Type 0.0 – Netlayer Baltrum: Laid down 1 Apr 1941; Requires 455 tons, 0 tons previously consumed; receives 255 tons, 200 tons remaining; Launched 26 May 1941
Pierside:
Refits:
At Bremerhaven
Refit of Light Cruiser Bremen: Refit commences 10 Apr 1941: Requires 1,173 tons, 0 tons previously consumed; Receives 1,173 tons, 0 tons remaining; Refit complete 22 Jun 1941 and commences post-refit trials
Conversions:
At Bremerhaven
Conversion of mercantile hull as Advanced Base Ship Coronel: Conversion commences 1 Jan 1941: Requires 2,319 tons, 1,160 tons previously consumed; Receives 1,159 tons, 0 tons remaining; Conversion completed 18 May 1941 and commences post-conversion trials
Conversion of mercantile hull as Advanced Base Ship Moon-sund: Conversion commences 1 Apr 1941: Requires 2,319 tons, 0 tons previously consumed; Receives 1,160 tons, 1,159 tons remaining
At Hamburg
Conversion of mercantile hull as Armament Store Issuing Ship Sachsenwald: Conversion commences 1 Apr 1941: Requires 1,099 tons, 0 tons previously consumed; Receives 550 tons, 549 tons remaining.
At Memel
Conversion of mercantile hull as Minelayer Support Ship Radetzky: Conversion commences 1 Jan 1941: Requires 1,395 tons, 698 tons previously consumed; Receives 697 tons, 0 tons remaining; Conversion completed 20 Apr 1941 and commences post-conversion trials
At Wilhelmshaven
Conversion of mercantile hull as Victualing Store Issuing Ship Mittenwalde: Conversion commences 1 Jan 1941: Requires 1,099 tons, 550 tons previously consumed; Receives 549 tons, 0 tons remaining; Conversion completed 11 Apr 1941 and commences post-conversion trials
Conversion of mercantile hull as Victualing Store Issuing Ship Eichwalde: Conversion commences 1 Apr 1941: Requires 1,099 tons, 0 tons previously consumed; Receives 550 tons, 549 tons remaining.
Small Craft Acquisitions:
None
D. Transactions
Tonnage Received from Argentina for construction of battlecruisers: 2,190
Tonnage Received from Brazil for construction of battlecruisers: 4,380
Tonnage Received from France for sale of Schnellboote 200
Tonnage Received from Peru for construction of a light cruiser: 1,600
Tonnage Received from Turkey for sale of Emden class cruisers: 2,000 (final payment)
Tonnage Received from Turkey for sale of R-1 class minesweepers 1,200
E. Other Notes
Ships Laid Down This Quarter
At Bremerhaven: Destroyer Marburg, Destroyer Konstanz
At Cuxhaven: Destroyer Tubingen, Destroyer Weilheim
At Hamburg: Minesweeper Schwielowsee, Minesweeper Werbellinsee
At Memel: Icebreaker Pollux, Netlayer Norderney, Netlayer Baltrum
Ships Launched This Quarter
At Hamburg: Minesweeper Schwielowsee, Minesweeper Werbellinsee
At Kiel: Destroyer Lindau, Destroyer Schleswig
At Memel: Icebreaker Castor, Netlayer Norderney, Netlayer Baltrum
At Wilhelmshaven: Coastal U-boat U-201, Coastal U-boat U-202
Ships Completed This Quarter
At Hamburg: Destroyer Paderborn, Destroyer Gottingen, Minesweeper Fleesensee, Minesweeper Rhinsee
At Kiel: Battlecruiser Viencente de Mayo (Argentine account), Light cruiser Magdeburg
At Wilhelmshaven: Light cruiser Lubeck
Refits/Conversions
Light Cruiser Bremen (completed)
Advanced Base Ship Coronel (completed)
Advanced Base Ship Moon-sund (in process)
Minelayer Support Ship Radetzky (completed)
Victualing Store Issuing Ship Mittenwalde (completed)
Victualing Store Issuing Ship Eichwalde (in process)
Armament Store Issuing Ship Sachsenwald (in process)
Ships Completing Trials This Quarter
Light cruiser Koln (post refit)
Destroyer Zerstorer 264
Destroyer Zerstorer 265
Minesweeper Blankensee
Minesweeper Muggelsee
Coastal Escort Mehrzweckboot 3
Coastal Escort Mehrzweckboot 4
Tender Saar
Sail Training Ship Seeadler
Victualing Store Issuing Ship Mittenwalde (post conversion)
Minelayer Support Ship Radetzky (post conversion)
Ships Retired to the Reserve or Disposed Of
Twelve Schnellboote sold to France
F. Scrappage Report
None this quarter
Updated Order of Battle
Type : In Service + Trials + Building + Refitting = Total
Battleships : 4 + 0 + 4 + 0 = 8
Battlecruisers : 4 + 0 + 0 + 0 = 4
Aircraft Carriers : 2 + 0 + 0 + 0 = 4
Heavy Cruisers : 4 + 0 + 0 + 0 = 4
Light Cruisers : 9 + 2 + 4 + 1 = 16
Heavy Destroyers : 18 + 0 + 0 + 0 = 18
Destroyers : 42 + 2 + 8 + 0 = 52
Torpedo boats : 20 + 0 + 0 + 0 = 20
Escort Ships : 34 + 0 + 0 + 0 = 34
Submarines : 58 + 2 + 1 + 0 = 61
Destroyer-Minelayers : 4 + 0 + 0 + 0 = 4
Minecraft : 66 + 2 + 2 + 0 = 70
Coastal Gunboats : 4 + 0 + 0 + 0 = 4
Motor Torpedo Boats : 38 + 0 + 0 + 0 = 38 (twelve boats to France)
River Gun Boats : 2 + 0 + 0 + 0 = 2
River Patrol Boats : 6 + 0 + 0 + 0 = 6
MTB Tenders : 3 + 0 + 0 + 0 = 3
Submarine Tenders : 3 + 0 + 0 + 0 = 3
Replenishment Ships : 6 + 0 + 4 + 0 = 10
Minelayer Support Ship : 1 + 0 + 0 + 0 = 1
Advanced Base Ship : 0 + 1 + 1 + 0 = 2
Victualing Store Issuing Ship : 1 + 0 + 1 + 0 = 2
Armament Store Issuing Ship : 0 + 0 + 1 + 0 = 1
Icebreaker : 0 + 1 + 1 + 0 = 2
Netlayer : 0 + 0 + 2 + 0 = 2
Sturm Landungsboot : 10 + 0 + 0 + 0 = 10
Pionier Landungsboot : 10 + 0 + 0 + 0 = 10
Flieger-schuleschiffe : 1 + 0 + 0 + 0 = 1
Artillerie-schuleschiffe : 0 + 2 + 0 + 0 = 2
Segel-schuleschiffe : 1 + 1 + 0 + 0 = 2
Zielschiffe : 1 + 0 + 0 + 0 = 1
Hafen-schuleschiffe : 1 + 0 + 0 + 0 = 1
Significant Changes:
Refit program for Koln class light cruisers continues. Additional mercantile conversions for auxiliaries put in hand.